MES validation,phase by phase.

Every POMS project follows the GAMP 5 V-model, with the documents and testing your validation team needs in each phase.

Validation engineer in a cleanroom coverall reading a test step on a rugged tablet beside a stainless steel scale with a test weightConceptual view

Traceability matrix

REQ-012

Dispensed weight stays within limits

  • Functional specFS-4.3Approved
  • IQ testIQ-007Pass
  • OQ testOQ-014Pass
  • PQ testPQ-003Pass
Design and tests linkedTraced

Standards we work to

GAMP 5
Risk-based validation
cGMP
Good manufacturing practice
21 CFR Part 11
Electronic records and signatures
EU Annex 11
Computerised systems
ISA-88
Recipes
ISA-95
Plant and enterprise systems

Our services team averages 15+ years implementing POMSnet in life sciences.

Every specificationhas its test.

GAMP 5 pairs each specification with the test that verifies it. Choose one to see how it is proven.

Specify, on the way downVerify, on the way up

01 / 04

User requirementsPerformance qualification

What the MES must do at your site, tested in performance qualification.

Specified in
Functional requirements and fit analysis
03 Analysis
Proven by
PQ support at go-live
07 Commissioning

The traceability matrix ties each requirement to its design and its test.

How a project runs

What you getin each phase.

Standard deliverables in every phase. A quality lead on every project keeps them in line with your quality plan and the regulations.

  1. 01

    Concept

    • Proposal
    • Budget estimate
  2. 02

    Planning

    • Project plan
    • Quality plan
    • Detailed project schedule
  3. 03

    Analysis

    • Functional requirements and fit analysis
    • Traceability matrix
    • Blueprint
    • EBR prototype
  4. 04

    Design

    • Functional design specification
    • Interface design specification
    • Infrastructure design specification
    • Data plan
    • Updated traceability matrix
  5. 05

    Implementation

    IQOQ
    • System configuration
    • Installation verification manual
    • Risk-based factory acceptance testing
  6. 06

    Customer installation

    IQOQ
    • Validation system setup
    • IQ and OQ at your site
  7. 07

    Commissioning

    PQ
    • Production system setup
    • Data migration
    • Go-live
    • PQ support

IQ, OQ and PQ: installation, operational and performance qualification.

Test wherethe risk is.

Walk through each instruction with an operator and a quality reviewer: what could go wrong, and which control catches it?

Operator and quality reviewer in cleanroom gowns walking through an instruction at a stainless steel process skid
  1. 01High risk

    Test thoroughly.

    Limits, identity checks, signatures and calculations that affect product quality.

  2. 02Medium risk

    Test the main paths.

    Workflow and status logic that supports GMP decisions.

  3. 03Low risk

    Rely on supplier testing.

    Display and convenience features.

Where an MESsits in GAMP 5.

A configurable MES such as POMSnet Aquila is usually treated as category 4. Your own assessment decides.

1Infrastructure softwareOperating systems, databases, middleware
3Non-configured productsStandard tools used as supplied
4Configured productsPOMSnet Aquila recipes, phases, roles and workflows, set up through configurationUsually POMSnet Aquila
5Custom applicationsAny custom code, which a configured MES aims to avoid
  1. 01

    Start with intended use.

    What the MES will do at your site, and which decisions depend on its records.

  2. 02

    Use what the supplier provides.

    A configured product is tested by its supplier before release. Your validation can rely on that testing and focus on your configuration.

Keep itvalidated.

After go-live, change control, periodic review and risk-based testing of upgrades keep the system in a validated state.

  1. 01

    Change control

    Assess each change, then test what it affects.

  2. 02

    Periodic review

    A POMS health check reviews your installation, configuration and performance.

  3. 03

    Upgrades

    With the Product Validation Kit, you validate the change, not the whole system.

  4. 04

    On your schedule

    POMS never forces an upgrade, so you plan each one with your validation team.

Thin on validation resources?

Our validation and test engineers can join your team, with the latest product know-how.

Talk to us
Validation
Documents and testing for new products, sites and releases.
Testing
Test scripts and execution for configuration changes and upgrades.

Questions validation teams ask

What GAMP 5 category is an MES?

A configurable MES such as POMSnet Aquila is usually treated as GAMP category 4, configured software. Any custom-coded parts would be category 5. Your validation approach should follow your own assessment.

Does POMS validate the system for us?

Validation is the manufacturer's responsibility. POMS provides documentation, testing and validation services, and its project methodology follows the GAMP 5 V-model.

Do we have to revalidate everything at each upgrade?

No. A risk-based approach focuses testing on what changed and what it affects. Release notes help you assess each change.

What does the Product Validation Kit cover?

It provides operational qualification (OQ) of the core standard product, so your own testing can focus on your configuration, your intended use and what changed.

Plan yourvalidation.

Talk to POMS about the documentation and testing you need.